Delays on airport project - WALB.com, Albany News, Weather, Sports

Delays on airport project

  • More WALB News10 HeadlinesMore News Headlines

  • Thursday, May 23 2013 4:17 PM EDT2013-05-23 20:17:43 GMT
    In 2007, Phoebe Sumter Medical Center was in the same situation Moore Medical in Oklahoma is in now. Phoebe Sumter is taking up funds and signing a banner to send to Moore, Oklahoma Medical next week.
    In 2007, Phoebe Sumter Medical Center was in the same situation Moore Medical in Oklahoma is in now. Phoebe Sumter is taking up funds and signing a banner to send to Moore, Oklahoma Medical next week.
  • Thursday, May 23 2013 3:54 PM EDT2013-05-23 19:54:34 GMT
    A Dougherty County rape crisis center hopes to raise $15,000 at a tasty event Thursday night at the Merry Acres Event Center. The Lily Pad Center provides support services to more than 300 child victims
     The Lily Pad Center provides support services to more than 300 child victims and roughly 150 adults every year. About two hundred people are expected to show up for the fourth annual 'Farm to Fork' Fundraiser.
  • Thursday, May 23 2013 2:33 PM EDT2013-05-23 18:33:20 GMT
    Three Albany men, charged with beating a man in a bar parking lot so viciously they fractured his skull. are found guilty of different levels of involvement in their trial. After three hours of deliberation
    A guilty verdict after three hours of deliberation, as three Albany men are found guilty of different levels of involvement in their aggravated assault trial.

April 16, 2003

Albany-- Work on a one million dollar project at the Southwest Georgia Regional Airport in Albany is far behind schedule.

Phase Two of the new airport cargo area was supposed to be finished March 19th. But a city inspector estimates the project is just six percent complete.

Construction was underway on the new aircraft cargo area, "It's going slowly its going very slowly."

Airport Director Richard Howell says that work on Phase Two of the project was suppose to be done a month ago. The construction company, Wriley and Ephraim, got an extension, now they have until April 28th. But, they won't be done by then either. Howell says, "By our best estimation, and something has been happening out there, we've got about five to six percent of the project is completed."

Phase One of the airport project is100,000 square feet of concrete. Right next to it is an expanse of gravel and dirt. Well, in just 12 days, this dirt is suppose to look like this concrete."

"No, we will not be able to complete by April 28th."

Project Manager Bob White admits the work won't be done by April 28th--now they want another extension. Delays caused by rain and personnel problems are to blame--but White says the project is further along than people think, "No we are much more than six percent complete, about 30 percent complete."

Airport Director Richard Howell says, "But, bottom line is we are at day 145 and the project hasn't been done yet." The project, no matter who completes it, will be done--the federal government is paying the bulk of the cost. Just when it will be done, however, is the question.

Airport Director Richard Howell says UPS is set to move out to the new cargo area when it's complete. That will bring at least 250,000 dollars of revenue to the airport each year--but Howell says the longer the project is delayed, the more money the airport will lose.

Posted at 4:30 p.m. by melissa.kill@walb.com